San Miguel Corp. (SMC) is positioning itself to challenge Consunji-controlled Semirara Mining and Power Corp. (SMPC) for control of the country’s largest coal mine, as the government moves to auction 18 coal blocks under stricter requirements.

Four companies under the conglomerate led by tycoon Ramon Ang—Malita Power Inc., Limay Power Inc., SMC Powergen Inc. and San Miguel Global Power Holdings Corp. (SMGP)—attended the Department of Energy’s (DOE) pre-bid conference, signaling the group’s interest in the closely watched auction.

SMC chairman Ang earlier confirmed the group’s intention to participate in the bidding, although he said he had yet to study the auction’s terms of reference.

SMPC, meanwhile, is also seeking to participate despite opposing several provisions of the new bidding rules, particularly those requiring incumbent operators to surrender certain mining assets to the government.

The auction covers 18 coal blocks across Antique, Cagayan and Isabela, including 10 blocks on Semirara Island in Caluya, Antique, where SMPC has operated for decades. The remaining areas comprise three blocks in Amulung and Iguig, Cagayan, and five in Benito Soliven, Naguilian and Cauayan, Isabela.

SMPC’s existing coal operating contract, known as COC No. 5, expires on July 14, 2027, ending its 50-year operating arrangement. The auction will determine whether the company retains its position or gives way to a new operator.

Asset Turnover Dispute

SMPC chairman Isidro Consunji described the company’s predicament as a “Catch-22,” referring to what he sees as a no-win situation under the DOE’s new bidding requirements.

The company said it was contesting provisions requiring incumbent operators seeking to retain their existing areas, either directly or through affiliates, to account for and surrender assets, equipment and facilities that have been fully or partially cost-recovered, amortized or depreciated.

SMPC claimed the DOE expanded the asset-surrender requirement to cover its power plant, pier, trucks, and heavy equipment, as well as proprietary know-how. It also objected to a requirement for SMPC and its affiliates to waive their constitutional and legal rights to challenge aspects of the bidding process in court.

“At a time when the country is the focus of the whole world, here comes the DOE issuing this ill-advised confiscatory and outright illegal provision apparently to keep us out of the bidding,” SMPC said in a statement.

The company argued that Presidential Decree 972 allows it one year after the expiration of its coal contract to remove its assets. It maintained that the new provisions conflict with this existing legal protection.

SMPC also questioned the DOE’s decision to give greater weight to financial offers rather than technical experience, saying the revised criteria could disadvantage established operators.

“These illegal bid rules will not stand in court. The DOE is going out on a limb for zero gain for the country and the people. A win based on a wrong is defeat in the end,” the company said.

The DOE, however, maintained that the asset turnover requirement was intended to put all bidders on equal footing. Energy Undersecretary Alessandro Sales said the provision would prevent incumbent operators from enjoying an advantage over competing companies through the continued use of existing facilities.

Under the rules, the DOE also said the requirement would not override court decisions concerning asset ownership or disposition. The agency added that it would assume no liability if an incumbent operator refused or failed to comply.

During the pre-bid conference, an SMGP representative welcomed the requirement but sought clarification on whether it covered immovable facilities such as the pier and dewatering system, which are essential to mining operations.

The representative also urged the DOE to independently verify the inventory of assets to be surrendered rather than treating the incumbent operator’s submitted list as “final and conclusive.”

SMPC had previously rejected the DOE’s request for an inventory of its assets, arguing that the auction covers only 10 coal blocks on Semirara Island.

Tougher Requirements

Apart from the asset dispute, the new auction rules impose substantial financial and operational commitments on prospective coal operators.

Under Joint Administrative Order 2026-01, winning bidders must pay a non-refundable signing bonus of ₱1 billion and remit at least 30 percent of net proceeds to the government. Financial offers falling below the prescribed minimum threshold will automatically be rejected.

For the Semirara blocks, bidders must commit to producing at least 60 million metric tons of coal over a five-year work program, supported by corresponding mine development, infrastructure, manpower and budget plans.

At least 35 percent of annual coal production must also be sold or supplied to domestic buyers throughout the contract period. Failure to meet the domestic supply requirement could result in the cancellation of the coal operating contract.

Applicants must demonstrate sufficient working capital to cover their first-year operating budget, employ qualified personnel, and possess at least five years of relevant industry experience.

The requirements come as SMPC confronts operational and financial pressures. Since the DOE announced the auction, the company’s share price has declined, while it has suspended production at its Acacia Mine in Antique because of flooding and reduced its capital expenditure.

San Miguel’s potential entry adds another layer of competition to the auction, although it remains unclear which coal blocks its subsidiaries intend to pursue or whether they will submit formal bids.

Other participants at the pre-bid conference included DESCO Inc., a Filipino-owned engineering and industrial services firm, and Eurodite, an international engineering and construction management consultancy.

The DOE has scheduled the submission and opening of bids for Dec. 11, followed by the announcement of qualified bidders on Dec. 16. Financial proposals will be opened on Dec. 21, with the highest-rated qualified bidder expected to be declared on Dec. 28.

The notice of award is scheduled for Jan. 11, 2027, setting the stage for a potentially significant shift in ownership and operations in the country’s coal industry.

Source:

https://www.philstar.com/business/2026/11/14/2569936/smc-mobilizes-4-firms-coal-mine-auction

https://businessmirror.com.ph/2026/11/16/coal-bid-rules-frustrate-smpc

https://bilyonaryo.com/coal-war-brewing-ramon-ang-sid-consunji-join-semirara-bidding-talks/

Share this article